May 17, 2022 - June 30, 2022

Demolition will start on May 19th on the 3rd floor restrooms of Greene Hall – Men’s and Women’s. These restrooms will be inaccessible for the duration of the project – WFU employees and visitors should use restrooms on the 2nd or 4th floors of Greene Hall instead.

The contractor expects to be able to compete demo in one day on May 19 but may spill over into Friday, May 20th as well – this will be a
very noisy part of the renovation. Currently, barring any unforeseen circumstances, final inspections should be completed by June 17th with a couple of days for punch list items after that. We anticipate having the restrooms operational again by July 1 at the latest.

Please contact Kim Jackson, WFU Project Manager at jackkv@wfu.edu for questions or concerns.