Parking Lot Closure Lot F

October 12, 2023 - April 1, 2025

WFU Facilities wanted to notify campus regarding a major project to renovate the South Chiller Plant, which is scheduled to begin on October 12, 2023 and complete on April 1, 2025. The project will bring much-needed improvements and upgrades to the HVAC cooling capacity and efficiency for all of Reynolda campus. As a result of the project, almost half of Lot F will be used by the contractor for construction materials, equipment, and crews during this time.

We apologize for the inconvenience and thank you for your understanding as we upgrade this important utility for campus.

Please contact Chris Looper (x4960) with any thoughts or questions.

Construction Polo Hall North Stairwell Exterior

February 1, 2024 - December 31, 2024

There will be some equipment stationed on the North side of Polo at the end of the wing facing Martin for exploratory work on the metal cladding around the windows on the stairwell. The Contractor will be removing metal panels as part of investigation for repair work to windows and metal panels to occur this summer. All work will be on the exterior side of the stairwell.

Construction Deliveries

March 18, 2024 - August 2, 2024

WFU Facilities would like to notify campus partners for construction material deliveries regarding upgrades to the South Chiller Plant, which is located to the east of parking lot F by the football practice fields. Starting on Monday, March 18th, 18 wheeler flat bed trucks will deliver construction materials to the South Chiller Plant job site. The trucks will make several deliveries each day, entering campus from the University Parkway gate and taking a left on McPherson Rd toward Lot F. Construction crews will need to temporarily stop traffic in both directions on McPherson Rd to allow for the truck to back down into Lot F toward the job site and again to leave Lot F back onto McPherson Rd to exit campus. The daily deliveries will start on March 18th and end the first week of August. We apologize for the inconvenience and thank you for your patience as we upgrade critical infrastructure to Reynolda Campus.

Contact Chris Looper (x4960) (looperc@wfu.edu) with any questions or concerns.

90min Light test

May 20, 2024 - June 4, 2024

This is the annual 90 min. Lighting test
Power outages will occur during the specified time, allowing us to conduct the necessary inspections and/or repairs required by the state code.

5/20 6:00-8:00 AM Luter Hall, Angelou Hall
5/21 6:00-8:00 AM Davis Hall, Taylor Hall, Efrid Hall
5/22 6:00-8:00 AM Polo Hall, Martin Hall, Student Apt.
5/23 6:00-8:00 AM Kitchin Hall, Poteat Hall, Huffman Hall
5/24 6:00-8:00 AM North Campus Apartments, Babcock Hall
5/28 6:00-8:00 AM Dogwood Hall, Magnolia Hall
6/3  6:00-8:00 AM Collins Hall, Bostwick Hall, Johnson Hall

Steam Outage

May 24, 2024 - May 20, 2024

Steam System Outage Monday May 20, 2024 3PM through Friday May 24, 2024.
The Wake Forest University Central Heating Plant annual shut down for maintenance and inspections will begin on Monday, May 20, 2024, at 3pm. The steam outage will disable building heating and domestic hot water systems campus wide. The boilers will be restarted Friday, May 24, 2024. Barring any delays, steam pressure will be back to normal by 6pm on Friday.