December 19, 2023 - January 4, 2024

Alumni Hall Electrical Power Interruptions
As part of the Alumni Hall Generator / ATS / UPS renewal replacement project, we will be completing final electrical load transfers to new equipment and system operational testing. Scheduled for Tuesday December 19, 2023, Wednesday December 20, 2023 and Thursday January 4th, 2024.

What to expect:
Tuesday December 19, 2023 8AM to 4PM UPS B load transfers
Power interruption limited to partial IS equipment and communication center.
General Building Power NO interruption.

Wednesday December 20, 2023 8AM to 4PM UPS A Load Transfers
Power interruption limited to partial IS equipment.
Campus Wide Stream 2 CATV Outage for the duration of this work
General Building Power NO interruption.

Thursday January 4th, 2024 9AM to 12PM Power Outage to Building, Systems test
Total Building Power Outage
Power will be turned off to the Alumni Hall building at 9AM, circuits and systems currently back up by generator will remain in service during the outage. We expect testing to be complete by Noon and power restored to normal.